Party Wall Agreements: Notices, Consent and Awards Explained

Gavin RogersBy Gavin RogersChecked 19 October 2026

  • Know the price before you're quoted
  • Free quotes from local trades
  • No obligation to go ahead
  • Honest prices, checked monthly
In this guide and more guides

The Short Answer

If your work touches a wall you share with a neighbour, builds a wall on the boundary, or digs near their foundations, the Party Wall etc. Act 1996 says you must serve them a notice first: 2 months before work on a shared wall, 1 month before a new boundary wall or excavation. It applies in England and Wales.

The Act doesn't mention a "party wall agreement". Either your neighbour consents in writing within 14 days, which costs nothing, or they don't, and surveyors draw up a party wall award, usually at your expense. Talk to them before the notice arrives: it's the cheapest thing you'll do on the whole project.

CheckerDo I need a party wall notice?Answer one or two questions about the work. This applies the three tests in the Party Wall etc. Act 1996 (England and Wales).
What will the work do?

Yes: a party structure notice, at least 2 months before you start.

Work to a wall (or floor) you share is section 2 of the Act. Your neighbour has 14 days to consent in writing. If they don't, a dispute is deemed to have arisen and surveyors decide how the work is done. They can also ask for extra work within 1 month (a counter notice), which they pay for.

A notice lapses if the work hasn't started within 12 months. Work can start earlier than the notice period only if your neighbour agrees in writing. Neighbours include freeholders and leaseholders with a lease of more than a year: notify every one.

Agreement, consent or award: what you actually need

"Party wall agreement" is what most people call it, but the Act doesn't use the phrase. What it sets out is a notice from you, then one of two outcomes:

  • Written consent. Your neighbour agrees, in writing, to what your notice describes. No surveyors and no fees. That's the end of the formal process, though you still have the duties below while the work goes on.
  • A party wall award. If they don't consent, the Act treats it as a dispute and one or more surveyors settle it with an award: a legal document setting out what you can do, how and when, and who pays.

You'll see "agreement" and "award" used as if they were the same thing. They aren't, and the difference matters to your budget: consent is free, an award usually means paying for your neighbour's surveyor as well as your own.

The Act is separate from planning permission and building regulations. Having either doesn't remove the need for a notice, and a notice doesn't give you either. Councils don't have to tell you about the Act, so don't count on a reminder from them.

Work that needs a notice

A loft conversion under way in a Victorian terrace: a red steel beam built into a pocket in the brick party wall, resting on a concrete padstone, with new timber floor joists alongside
Steels bearing into a party wall, as here in a loft conversion, need a party structure notice.

The Act covers three kinds of work, and one job can involve more than one:

  • Work on an existing party wall or party structure (section 2). Cutting into it to take the end of a beam, raising it, underpinning it, putting in a damp-proof course, cutting off a projecting chimney breast, or demolishing and rebuilding it. Notice: at least 2 months.
  • A new wall on the boundary (section 1), whether it stands astride the line or wholly on your side up to it. Notice: at least 1 month. You can only build astride the line with your neighbour's written consent.
  • Digging near their building (section 6). Within 3m of it and deeper than the bottom of its foundations, or within 6m and reaching below a line drawn down at 45 degrees from the bottom of its foundations. Notice: at least 1 month, with plans and sections.
When digging near a neighbour needs a party wall noticeA cross-section. On the left, the neighbour's house and its foundations. Within 3 metres of their building, digging deeper than the bottom of their foundations needs a notice. Within 6 metres, digging that reaches below a line drawn down at 45 degrees from the bottom of their foundations needs a notice.Their housebottom of theirfoundations45°3m6mNotice if you digdeeper than theirfoundationsNotice if you digbelow the 45° line
Section 6 of the Party Wall etc. Act 1996, drawn to scale. Distances are measured horizontally from any part of the neighbour's building. Not to be used instead of a designer's or engineer's check.

A party wall is a wall that stands across the boundary (part of a building, or a masonry garden wall shared by both of you, but not a wooden fence or a hedge), or a wall on one owner's land that both of you use to separate your buildings. Floors between flats count too: the Act calls them party structures.

Minor work usually doesn't need a notice: drilling for shelves, cutting in sockets, replastering. The government's explanatory booklet puts the test as whether the work could affect the wall's strength or damage your neighbour's side.

Common projects

  • Loft conversions almost always need a 2-month notice, because the new floor and roof steels often bear into the party wall. It's the booklet's own example.
  • Extensions often need an excavation notice for the foundations, and a boundary wall notice if the side wall goes on or up to the line. Side returns usually need both.
  • Removing a chimney breast from a party wall is on the government's list of work you must tell your neighbour about.
  • Conservatories, garden walls and new roofs need a notice only if they meet one of the three tests: a conservatory with foundations close enough and deep enough, a masonry wall on the boundary, or roof work that cuts into or raises the party wall. Re-roofing on its own isn't on the list.

Serving the notice

There's no official form, and you don't need a professional to write or serve it. The booklet has example letters for each kind of notice. Whatever you use, it should include:

  • your name and address (every joint owner, by name);
  • the address of the property being worked on, if different;
  • a full description of the work, with plans (plans and sections are required for an excavation notice);
  • the date you plan to start, no earlier than the notice period allows;
  • the date of the notice, and a clear statement that it's a notice under the Party Wall etc. Act 1996.

Hand it over in person or post it. Email is allowed only if your neighbour has said they're happy to receive notices that way and given you the address. If you don't know who owns the property, you can address it to "The Owner" and leave it there.

Serve every adjoining owner. That includes a freeholder and a leaseholder of the same house (anyone with a lease of more than a year), and for excavation, owners within the distances even if their building doesn't touch yours.

Timing cuts both ways. Work can't start before the notice period ends unless your neighbour agrees in writing, and a notice lapses if the work hasn't started within 12 months. We'd serve it once your drawings are settled, not the day you first have the idea.

What your neighbour can do

Once the notice is served, your neighbour can:

  • Consent in writing within 14 days. You can then go ahead when the notice period ends.
  • Refuse, which starts the dispute process below.
  • Serve a counter notice within 1 month, asking for extra work for their own benefit (they pay for it). You have 14 days to agree to it.
  • Say nothing. Silence isn't consent. For work on a party wall or an excavation, no written consent within 14 days means a dispute is deemed to have arisen. For a new wall astride the boundary, it means you can only build wholly on your own land, at your own expense.

They can't stop work the Act allows, but they can shape how and when it's done. Consenting doesn't cost them any rights either: if something goes wrong later, damage for instance, they can still use the dispute process.

If they don't consent: surveyors and the award

A dispute is settled by surveyors, in one of two ways:

  • One agreed surveyor, who both of you appoint. Cheaper, and the booklet suggests it for small residential jobs where fees would add a lot to the cost.
  • One surveyor each, who then select a third. The third is only called in if the first two can't agree, or either of you asks.

A surveyor can be almost anyone who isn't a party to the matter, but not you, and the booklet advises against using whoever is supervising the build. Every surveyor must act impartially, including the one you appoint. If your neighbour won't appoint one, ask them in writing: after 10 days you can appoint one on their behalf. Appointments are in writing and can't be withdrawn, so choose carefully.

The award sets out the work, when and how it's done, any protection needed, and who pays, including the surveyors' fees. It often includes a record of the condition of your neighbour's property before work starts, which is what any later damage claim is measured against. Keep a copy with your deeds.

Who pays. If the work is only for your benefit, you pay for it and, usually, for all the surveyors. Costs are shared when the wall needs work because of a defect or disrepair, and your neighbour pays for any extra work they ask for. There are no set fees; you can ask a surveyor for a breakdown. Our fee estimates for party wall surveyors are on our side return extension guide.

An award is final unless either of you appeals to the county court within 14 days of receiving it. The booklet warns that an appeal shouldn't be taken lightly: whoever loses may have to pay the other side's costs.

To find a surveyor, the booklet points to the Faculty of Party Wall Surveyors and the Pyramus & Thisbe Society, both of which can put you in touch with surveyors in your area, as well as RICS.

Once work starts

Consent or award, the Act puts the same duties on you while the work goes on:

  • No unnecessary inconvenience. The noise and mess the job can't avoid is allowed; anything beyond that isn't.
  • Protection and repairs. Where your work opens up their land or building, you must protect it. You're responsible for putting right any damage, even if your builder caused it, or paying for it instead if they ask.
  • Access. Your builders and surveyors can go onto their property during usual working hours to do the notified work, after 14 days' notice (less in an emergency). Knowingly refusing or obstructing entry is a criminal offence.
  • Security. Your neighbour can ask you to put up security, such as money or a bond, before you start, in case the job is left half-done. The booklet says it's usually kept for intrusive or complex work.

We'd photograph their side of the wall (with their permission) before any work starts, even if they've consented. It gives you both something to check against if a crack appears later.

If no notice was served, or you're selling

The Act has no enforcement procedure of its own. If someone starts work without serving notice, it's a civil matter: the neighbour can ask a court for an injunction to stop the work, or seek other legal remedies. If you think your neighbour is about to start without a notice, the booklet suggests telling them about the Act in writing first.

When you sell, the seller's property information form (the Law Society's TA6) asks about party wall notices, and the Law Society's notes say to attach any you served or received. If work was done and you can't find a notice, tell your solicitor.

The Act doesn't change who owns a wall or where the boundary is, and it can't settle a boundary dispute. Those go to the courts or to mediation.

What it costs

Prices, what moves them and who to hire, in our cost guides.

Free quotesGet house extension quotesExtensions are priced from size, storeys and finish. A few answers get you realistic quotes.
Question 1 of 11
What type of house?

Free, no obligation. We're paid by MyJobQuote when a tradesperson buys your job, never by you.

Frequently asked questions

Do I legally need a party wall agreement?

You legally need to serve a notice if your work is on a party wall, builds a new wall on the boundary, or digs within 3 or 6 metres of a neighbour's building deep enough to meet the Act's tests. What follows is either your neighbour's written consent or, if they don't consent within 14 days, a surveyor's award. "Agreement" isn't a term the Act uses.

Can I write my own party wall notice?

Yes. There's no official form and you don't need a surveyor or solicitor to serve it. The government's explanatory booklet has example letters. Include every owner's name, the address, a full description of the work (with plans for an excavation notice), the start date, the date of the notice, and a statement that it's a notice under the Party Wall etc. Act 1996.

How much does a party wall agreement cost?

If your neighbour consents in writing, nothing beyond your own time. If they don't, surveyors make an award, and if the work is only for your benefit you usually pay for your neighbour's surveyor as well as your own. There are no set fees. Our estimates for party wall surveyors are on our side return extension cost guide.

What can I do if my neighbour builds without a party wall notice?

Tell them about the Act in writing. If work has already started without a notice, the Act has no enforcement procedure of its own: it's a civil matter, and you can ask a court for an injunction to stop the work. Take legal advice before you do.

Do I need a party wall agreement for a loft conversion?

Usually. Steels for a loft conversion often bear into the party wall, which is work under section 2 of the Act and needs a notice at least 2 months before it starts. The government's booklet uses a loft conversion beam as its example.

Can my neighbour stop my extension with the Party Wall Act?

No. The Act lets you do the work it covers, and a neighbour can't stop it, but they can influence how and when it's done, through the award if they don't consent. Planning permission and building regulations are separate questions.

Does the Party Wall Act apply in Wales and Scotland?

It applies in England and Wales. Scotland has different rules.

How we checked this4 sources · 3 officialView sources

Rules come from the legislation and official guidance, read at source, and are linked where the guide states them. Practical advice comes from makers', trade bodies' and official guidance; where sources disagreed, we've said so. Prices aren't in our guides: they're on the cost pages linked above, each with its own sources. More on our method.

Got your price?
Get your quotes.

  • Up to three local tradespeople
  • Free, with no obligation to go ahead
  • Takes about two minutes

Start your quote

You never pay us. We're paid by MyJobQuote when a trade buys your job.